Summary
This summary sheet was last update on 04.01.24
Currently working on Finishing
Current Project Time 2608.45
Construction/Assembly Time 1827.35
Parts Manufacturing Time 354.50
Tools Manufacturing Time 62.60
Engine Rebuild/Install Time 364.00
Finishing/Assembly 0.00 0%
Cowling 181.25 100%
Canopy 138.00 100%
Controls 77.75 95%
Fuel System 116.25 100%
Tail Group
Construction/Assembly 126.25 100%
Parts Manufacturing 71.00 100%
197.25
Outboard Wings
Construction/Assembly 237.50 100%
Parts Manufacturing 181.00 100%
418.5
Center Wing
Construction/Assembly 184.50 100%
Parts (included in O-Wings)
Forward Fuselage
Construction/Assembly 300.00 100%
Parts (See Rear Fuselage)
Rear Fuselage
Construction/Assembly 123.85 100%
Parts Manufacturing 52.00 100%
175.85
Instruments and Electrical
Instrument Panel 107.00 100%
Electrical 181.00 100%
288
Miscellaneous
Construction/Assembly 54.00
Parts Manufacturing 50.50
104.50
Engine Rebuild/Installation 364.00 100%
Tools 62.60